In other news, the water meter has been installed, the siding is progressing, and 18 tonnes of gravel have been poured into the basement. To finish the basement floor, three inches of insulation will be added, followed by wire mesh, the tubes for the radiant in-floor heating, and four inches of concrete. In preparation for the drywallers, the roof will be tested for leaks, extra blocking will be added to some of the walls where we plan to put shelving and grab bars (the things that will keep us from falling in the shower when we're old), the gaps in the insulation will be fixed, and a couple of doors will be reframed to the right height.
Forward, ho!